Progress

Tue, Jul 14, 2026

RISK REVIEW12-May-2026
Overall progress43.8%
Schedule perf (SPI)99.4%
Days behind · Conv13 days
Days behind · MIVAN13 days
MIVAN complete12 / 324 (3.7%)
Combined by today: 2,756 done of 2,702 planned · +54 work-days ahead
01.7k3.4k5.1k6.8kTODAYNov '25Mar '26Jul '26Nov '26Mar '27Jul '27Nov '27Mar '28
Actual · to today
Progress vs Plan
2,592 actual of 2,580 planned work-days7 ahead (+254) · 13 on plan · 7 behind (−242), mostly B7,B8, B15,B16
164 actual of 122 planned work-days4 ahead (+59) · 22 on plan · 1 behind (−17), mostly B1,B2
■ Achieved■ Shortfall
Cumulative Progress by MonthMeasured in scheduled work-days — not billed or paid value.By Jul-2026, 2,756 of 3,322 planned work-days are complete — behind by 566 work-days (83% achieved).
MonthPlanned work-days till monthCompleted work-days till monthWork-day gap% achieved
Nov-20257083+13119%
Dec-2025380341-3990%
Jan-2026788638-15081%
Feb-20261,0541,124+70107%
Mar-20261,4601,610+150110%
Apr-20261,8622,017+155108%
May-20262,3622,374+12101%
Jun-20262,8462,756-9097%
Jul-20263,3222,756-56683%