RISK REVIEW21-Jul-2026
Overall progress61.1%
Schedule perf (SPI)93.8%
Days behind · Conv191 days
Days behind · MIVAN97 days
MIVAN complete24 / 324 (7.4%)
Combined by today: 3,009 done of 2,904 planned · +105 work-days ahead
Actual · to today
Progress vs Plan
Conventional ▸103% of plan
2,835 actual of 2,748 planned work-days7 ahead (+264) · 16 on plan · 4 behind (−177), mostly B15,B16, B7,B8
MIVAN ▸112% of plan
174 actual of 156 planned work-days2 ahead (+28) · 24 on plan · 1 behind (−10), mostly B1,B2
■ Achieved■ Shortfall