Progress

Mon, Sep 7, 2026

RISK REVIEW21-Jul-2026
Overall progress61.1%
Schedule perf (SPI)93.8%
Days behind · Conv191 days
Days behind · MIVAN97 days
MIVAN complete24 / 324 (7.4%)
Combined by today: 3,009 done of 2,904 planned · +105 work-days ahead
01.7k3.4k5.1k6.8kTODAYNov '25Mar '26Jul '26Nov '26Mar '27Jul '27Nov '27Mar '28
Actual · to today
Progress vs Plan
2,835 actual of 2,748 planned work-days7 ahead (+264) · 16 on plan · 4 behind (−177), mostly B15,B16, B7,B8
174 actual of 156 planned work-days2 ahead (+28) · 24 on plan · 1 behind (−10), mostly B1,B2
■ Achieved■ Shortfall
Cumulative Progress by MonthMeasured in scheduled work-days — not billed or paid value.By Sep-2026, 2,894 of 4,156 planned work-days are complete — behind by 1,262 work-days (70% achieved).
MonthPlanned work-days till monthCompleted work-days till monthWork-day gap% achieved
Nov-20257083+13119%
Dec-2025380341-3990%
Jan-2026788638-15081%
Feb-20261,0541,124+70107%
Mar-20261,4601,610+150110%
Apr-20261,8622,003+141108%
May-20262,3622,360-2100%
Jun-20262,8252,805-2099%
Jul-20263,2802,894-38688%
Aug-20263,7712,894-87777%
Sep-20264,1562,894-1,26270%