RISK REVIEW12-May-2026
Overall progress43.8%
Schedule perf (SPI)99.4%
Days behind · Conv13 days
Days behind · MIVAN13 days
MIVAN complete12 / 324 (3.7%)
Combined by today: 2,756 done of 2,702 planned · +54 work-days ahead
Actual · to today
Progress vs Plan
Conventional ▸100% of plan
2,592 actual of 2,580 planned work-days7 ahead (+254) · 13 on plan · 7 behind (−242), mostly B7,B8, B15,B16
MIVAN ▸134% of plan
164 actual of 122 planned work-days4 ahead (+59) · 22 on plan · 1 behind (−17), mostly B1,B2
■ Achieved■ Shortfall